City of Dallas
Dallas tenant improvement: finish-out permit and occupancy basics
A short, sourced summary of what the City of Dallas asks for when you finish out or remodel leased commercial space. Always confirm current requirements with the city before you apply.
Read this first
Permit rules change. The summary below comes from City of Dallas web pages and a city checklist, listed with links at the end of this page. The checklist we used carries a revision date of September 2021, and the city has since moved its permitting to an online system. Use this page to know what to ask, then confirm details with the city. We are a contractor, not the permitting authority, and nothing here is legal advice.
Who handles it
Commercial building permits in Dallas go through the city's permitting and inspection staff. The city's finish-out checklist names the Building Inspection Division of the Development Services Department, at the Oak Cliff Municipal Center, 320 E. Jefferson Blvd., Dallas, with the telephone number (214) 948-4480. City web pages also use other department names, so the office may have been renamed since that checklist was issued.
The city states that it now uses an online system called DallasNow for permitting services. According to the city, building permit and certificate of occupancy applications are submitted through it.
What the finish-out checklist asks for
Dallas publishes a checklist titled Commercial Building Finish-Out, Remodel and Renovations. Items it lists include:
- A scope of work, the building area in square feet by occupancy or use, the occupancy type if known, and the fire sprinkler status and intentions.
- Legible, fully dimensioned plans drawn to a standard scale, with design professional seals and signatures where required: a floor plan of the tenant space with each room identified by use, and either an existing-conditions plan or an interior demolition plan.
- A floor key plan showing where the tenant space sits among other suites on the floor, and a site plan. For a change in building use, the site plan covers the entire property.
- An asbestos survey for the area being renovated. The checklist says a permit cannot be issued before notification that a survey has been conducted.
- Proof that plans were submitted to the Texas Department of Licensing and Regulation (TDLR) for review against the Texas Accessibility Standards by a Registered Accessibility Specialist.
- Compliance with the Dallas Energy Conservation Code and Green Building Ordinance. For a first-time tenant finish-out, forms from registered third-party green building and energy code providers go in with the application. An Energy Code Compliance Certificate is required before the final inspection on all permits.
- Compliance with the EPA's lead renovation, repair and painting rule.
- Extra plans if the space will prepare, store or sell food or beverages.
The checklist also warns that incomplete applications cannot be accepted, and that a missing item not supplied within five working days after notice can lead to the application being discarded and refiled. Complete plans the first time matter.
TDLR accessibility registration
TDLR states that projects with an estimated total cost of $50,000 or more must be registered with TDLR and have construction documents reviewed by a Registered Accessibility Specialist. Below that amount, registration with TDLR is not required, but the project must still comply with the Texas Accessibility Standards, and a local building official can still ask for registration. Your design professional normally handles this filing.
Certificate of occupancy
A permit covers the construction. A certificate of occupancy, or CO, is about the use of the space. The city says a person may not use or change the use of a building, or part of one, without a CO from the building official, except single-family and duplex uses.
The city lists these situations as needing a new CO:
- the first use of land or a building,
- a change of use,
- a change of tenant on an existing CO, and
- a change that increases or decreases floor area.
So a new tenant moving into a previously occupied suite generally needs a CO in that tenant's name, even when the construction is light. The city says CO applications are made through DallasNow with a Land Use Questionnaire and the fee. If the use is the same as before, inspections can be scheduled once the application is approved and paid. If the use is different, the application also goes to building code and zoning reviewers and may need a site plan, floor plan or parking analysis. Temporary certificates of occupancy are reviewed and approved by the city's district managers.
Inspections
The city's CO page says the CO or temporary CO is released once all inspections pass. The finish-out checklist adds that the energy compliance certificate must be provided before final inspection. We have not listed which individual inspections apply to which scopes, because that depends on the work and is set by the city. Your permit tells you which inspections to schedule.
What we leave out
We did not find a current city source for permit fees or review times, so we state none. We also describe no neighborhoods or building types here, because we have not verified them against a source. On projects we build, we handle submittal of our scope's permit documents and coordinate inspections with the city. Who files what on your job is a contract decision, so settle it in the bid.
Keep reading
- Tenant improvement process
Where the permit sits in the full project timeline.
- Office build-outs
What gets built once the permit is issued.
Planning a Dallas build-out?
Walk-through, itemized bid, written scope. Se habla español.
See the full portfolio on the main site.